PERT Calculator: Three-Point Estimate and Deadline Probability

Three-point estimate (O + 4M + P)/6, standard deviation, a whole path of tasks and the probability of meeting a deadline.

Your details

Estimate

Deadline in the same unit, counted from the start, to get the chance of finishing on time.

Results update as you type

Expected duration E

7

Standard deviation σ
1.67
Variance σ²
2.7778
Probability of finishing by the target
88.49%
z score of the target
1.2
Duration at 80 % confidence
8.4
Duration at 95 % confidence
9.74
Triangular estimate (O + M + P)/3
8

All durations are in the unit of your estimates (hours, days, weeks…).

Step-by-step solution
  1. E = (4 + 4 × 6 + 14) ÷ 6 = 7
  2. σ = (14 − 4) ÷ 6 = 1.6667
  3. z = (9 − 7) ÷ 1.6667 = 1.2 → Φ(z) = 88.49 %

Duration by confidence level (normal approximation)

A single-number estimate hides the most important part of the answer: how uncertain it is. PERT (Program Evaluation and Review Technique), developed for the US Navy’s Polaris programme in the late 1950s, asks for three numbers instead. The optimistic time (O) if everything goes well, the most likely time (M) and the pessimistic time (P) if things go wrong. From them it derives an expected duration that leans toward the long tail, and a standard deviation that measures the risk.

This PERT calculator works for one task or for a path of several tasks done in sequence, such as the critical path of a project. It returns the expected duration, the standard deviation and the variance, the duration you can commit to at 80 % and 95 % confidence, and the probability of finishing by a target date using the normal approximation. For comparison it also shows the simpler triangular estimate, (O + M + P)/3.

Use any time unit you like (hours, days, sprints, weeks) as long as every estimate uses the same one. The method suits software, construction, events, research or anything else where durations are genuinely uncertain.

How to use this calculator

  1. Choose One task or Several tasks (path).
  2. For one task, enter the optimistic, most likely and pessimistic durations; they must satisfy O ≤ M ≤ P.
  3. For a path, add one row per task that must be finished before the next can start, with its three estimates. Name the rows if you like; blank rows are ignored.
  4. Optionally enter a target duration (your deadline, counted from the start).
  5. Read the expected duration E, the standard deviation, the chance of meeting the target, the 80 % and 95 % commitments and the triangular comparison. In path mode the table lists each task’s contribution; in single mode it gives the duration for several confidence levels.

The formula

For each activity, PERT approximates the duration by a beta distribution whose mean and standard deviation are:

E=O+4M+P6σ=P−O6σ2=(P−O6)2E = \frac{O + 4M + P}{6} \qquad \sigma = \frac{P - O}{6} \qquad \sigma^2 = \left(\frac{P - O}{6}\right)^2

For tasks performed in sequence, expected times and variances add up (assuming the tasks are independent):

Epath=∑Eiσpath=∑σi2E_{\text{path}} = \sum E_i \qquad \sigma_{\text{path}} = \sqrt{\sum \sigma_i^2}

By the central limit theorem the path duration is roughly normal, so the probability of finishing by a deadline DD is

P(T≤D)=Φ ⁣(D−Eσ)P(T \le D) = \Phi\!\left(\frac{D - E}{\sigma}\right)

and the duration at confidence cc is E+zc σE + z_c\,\sigma (for example z0.95=1.645z_{0.95} = 1.645). The triangular alternative weights the three points equally: Etri=(O+M+P)/3E_{\text{tri}} = (O + M + P)/3.

Worked example

One task estimated at 4, 6 and 14 days.

  • E=(4+4×6+14)/6=E = (4 + 4 \times 6 + 14)/6 = 7 days;
  • σ=(14−4)/6=1.67\sigma = (14 - 4)/6 = 1.67 days, variance 2.78;
  • probability of finishing within 9 days: z=(9−7)/1.667=1.2z = (9 - 7)/1.667 = 1.2, so 88.49 %;
  • duration at 95 % confidence: 9.74 days, while the triangular estimate gives 8 days.

A path of three tasks: design (2, 4, 6), build (5, 8, 17) and test (1, 3, 5). The expected durations are 4, 9 and 3, so Epath=E_{\text{path}} = 16 days. The variances 0.4444, 4 and 0.4444 add up to 4.8889, so σ=2.21\sigma = 2.21 days. The chance of finishing within 18 days is Φ(0.9045)=\Phi(0.9045) = 81.71 %, but committing to exactly 16 days gives only 50 %. To be 95 % sure, plan for 19.64 days. Summing the triangular estimates gives 17 days.

PERT versus triangular estimates

Both methods use the same three numbers. The PERT (beta) mean gives the most likely value four times the weight of the extremes, so it stays close to M and is less sensitive to an extreme pessimistic guess. The triangular mean treats all three points equally, so it moves further toward a long pessimistic tail and is usually the more cautious of the two when P is far from M. Neither is “right”: PERT is the classic choice taught in project management, while the triangular estimate is popular in Monte Carlo risk analysis. If they differ a lot, your estimates are strongly skewed and deserve a closer look.

Limits of the method

  • The normal approximation assumes several independent tasks; with one or two tasks the probabilities are only indicative.
  • PERT looks at one path. In a real network, a parallel path that is nearly critical can finish last, so the true probability of meeting the deadline is often lower than PERT suggests (merge bias). Simulation handles this better.
  • The result is only as good as the estimates. Ask the people who will do the work, write down assumptions, and check past projects for how often the pessimistic value was exceeded.

Frequently asked questions

What is the PERT formula?

Expected time E = (O + 4M + P) / 6, where O is the optimistic, M the most likely and P the pessimistic estimate. The standard deviation is (P − O) / 6 and the variance is its square.

How do I calculate the probability of finishing a project on time?

Add the expected times of the tasks on the critical path, add their variances and take the square root to get σ. Then compute z = (deadline − E) / σ and read the probability from the standard normal distribution; the calculator does this for you.

Why divide by 6?

The weights 1, 4 and 1 add up to 6, so dividing by 6 gives a weighted average. The (P − O)/6 standard deviation comes from assuming that the range from optimistic to pessimistic spans about six standard deviations, as for a roughly bell-shaped distribution.

Can I add standard deviations of tasks?

No. For independent tasks in sequence you add variances, then take the square root. Adding standard deviations overstates the risk of the path, because delays on one task are partly offset by gains on others.

What is the difference between PERT and the triangular three-point estimate?

PERT weights the most likely value four times: (O + 4M + P)/6. The triangular estimate weights all three equally: (O + M + P)/3. With skewed estimates the triangular result is usually longer.

Sources

Last updated:

More Other calculators

People also use