Mortar Calculator for Brick and Block Walls

Mortar for brick or block walls: volume, bags of premixed mortar or cement and sand for a site mix.

Your details

Unit system
Wall thickness

The Brick Industry Association suggests adding 15–25% to the theoretical mortar.

%
Mortar from

Results update as you type

Mortar to prepare

11.356 cu ft

Bags of premixed mortar
18
Net wall area
160 sq ft
Bricks or blocks (no waste)
1,080

Mortar estimates vary a lot with the mason, the bond pattern and the weather: keep one or two spare bags on site.

Step-by-step solution
  1. Wall area = 160 sq ft
  2. Units ≈ 1,080
  3. Mortar = 9.46 cu ft × 1.2 = 11.36 cu ft
  4. Bags = ⌈11.36 cu ft ÷ 0.66 cu ft⌉ = 18

Running out of mortar halfway up a wall means a second trip to the yard and a cold joint in the brickwork; buying far too much leaves bags hardening in the shed. This mortar calculator estimates the volume of mortar a wall needs from its area and the brick or block you lay, then converts it into bags of premixed mortar or into cement and sand for a site mix.

For bricks it uses the wall-area method of the Brick Industry Association: the mortar is the volume of the joints, that is the space between the brick and its module, multiplied by the wall area, plus a waste allowance for droppings and mortar left on the board. For hollow concrete blocks laid on their face shells, theory badly underestimates real use, so the calculator applies the field yields published by the concrete masonry industry instead.

To count the bricks themselves, use the brick calculator or the concrete block calculator; to batch a concrete slab or footing, use the cement calculator.

How to use this calculator

  1. Enter the wall length and height and the area of any openings.
  2. Choose the brick or block, or Custom size to type the unit dimensions and joint thickness.
  3. For bricks, choose a single or double wythe and a waste allowance (15–25% is typical).
  4. Choose Premixed bags and the bag size, or Cement + sand with the mix ratio and cement bag.
  5. Read the mortar volume, then the bags, or the cement and sand quantities.

The formula

For a unit of length ll, height hh and depth dd laid with joints jj, the module is (l+j)(h+j)(l + j)(h + j) and the mortar per square metre of single-wythe wall is

v=d(1−l h(l+j)(h+j))v = d\left(1 - \frac{l\,h}{(l + j)(h + j)}\right)

For a net wall area AA, nn wythes (a double wythe adds a solid collar joint of thickness jj) and a waste allowance ww:

V=A (n v+[n=2] j) (1+w)V = A\,(n\,v + [n = 2]\,j)\,(1 + w)

Bags =⌈V/Y⌉= \lceil V / Y \rceil, where YY is the bag yield. For a site mix 1:s1 : s, dry materials =1.33 V= 1.33\,V, cement =1.33 V/(1+s)= 1.33\,V/(1 + s) and sand =s= s times the cement volume.

Worked example

A 5 × 2.5 m wall with a 1.5 m² window, in 215 × 102.5 × 65 mm bricks with 10 mm joints, single wythe, 20% waste:

  • Net area 11 m², 59.3 bricks per m², about 652 bricks
  • Mortar: 17.6 L per m², so 193.8 L net and 232.5 L (0.233 m³) with waste
  • Premixed: 19 bags of 25 kg; or a 1:4 site mix: 89 kg of cement (3 bags of 35 kg) and 0.247 m³ of sand

US wall of 20 × 8 ft (160 sq ft) in modular brick: about 1,080 bricks, 9.46 cu ft of mortar in the joints, 11.36 cu ft with 20% waste, so 18 bags of 80 lb. The same wall in 8-in CMU: 180 blocks, 7.43 cu ft, 12 bags of 80 lb.

Mortar types M, S, N and O (ASTM C270)

ASTM C270 defines four mortar types, named from the letters of MaSoN wOrK, from strongest to weakest:

Type Minimum 28-day strength Cement–lime–sand proportions Typical use
M 2,500 psi (17.2 MPa) 1 : ¼ : 3¾ Below grade, foundations, retaining walls
S 1,800 psi (12.4 MPa) 1 : ½ : 4½ Structural walls, high wind or seismic zones, paving
N 750 psi (5.2 MPa) 1 : 1 : 6 Above-grade walls, veneer, most general work
O 350 psi (2.4 MPa) 1 : 2 : 9 Interior non-load-bearing walls, repointing soft brick

Stronger is not always better: the BIA recommends the weakest mortar that meets the structural needs, because softer mortar bonds and seals better and lets the wall move without cracking the bricks.

How much mortar per brick and per block?

In theory a modular brick wall takes about 5.5 cu ft of mortar per 100 sq ft (BIA Technical Note 10), or roughly 8 cu ft per 1,000 bricks, before waste. A wall of 215 × 65 mm European bricks with 10 mm joints takes about 18 L per m². Hollow 8-in blocks need much more per unit: CMHA TEK 04-02A states that one 80 lb bag of preblended mortar lays about 16 blocks, or about 50 brick-sized units. Manufacturers' bag labels give similar, slightly conservative counts.

Frequently asked questions

How much mortar do I need for 1,000 bricks?

For modular brick with 3/8 in joints, BIA Technical Note 10 gives about 8 cu ft of mortar in the joints (this calculator finds 8.8 from the exact brick size), or 10–11 cu ft with a 20–25% allowance: roughly 16 bags of 80 lb premixed mortar. Larger bricks or thicker joints need more.

How many bags of mortar per block?

With face-shell bedding, one 80 lb bag of preblended mortar lays about 16 standard 8 × 8 × 16 in blocks, so about 6–7 bags per 100 blocks. A 70 lb bag of masonry cement mixed with sand lays about 30 blocks.

What is the best mortar mix ratio?

For general brickwork, 1 part cement to 4 parts sand (or a Type N cement–lime mortar, 1 : 1 : 6) is a good default. Use 1:3 for below-grade or heavily loaded work and 1:5 or 1:6 with lime for soft bricks and interior walls.

Why add 15–25% waste to mortar?

Mortar is lost when it drops from the trowel, stiffens on the board, fills brick frogs and cores, or is struck off the joints. The Brick Industry Association recommends adding 15–25% to the theoretical quantity.

Is mortar the same as concrete?

No. Mortar is cement, lime and fine sand, made to bond and bed masonry units. Concrete contains coarse gravel and is made for strength in slabs and footings; use the cement calculator for concrete mixes.